Project Description

GWS Scout Camp Update 20/2/16

Provider: Job Prospects
Supervisor: John Tyson

It has been a great pleasure to undertake this project, work carried out so far…

  • Replaced handrails to chalet
  • Remove old retaining wall around memorial
  • Excavated front of Memorial and dug drainage pit
  • Installed silt box and unblocked pipe running under the road to lake
  • Jetty was leaning badly to the left
  • Used roped and ratchet strap to straighten and install bracing underneath
  • Installed hand rails and new post to end of jetty

See a selection of images taken during the project.